摘要: 在综采工作面作业中,经常会受到中部揭露陷落柱的影响而导致推采工作无法顺利进行。为此,需要引入回
采过地质构造分段回撤技术来提高综采工作面的安全性,减少不必要的损失。通过对实际案例的分析和方案对比,对综
采过地质构造分段回撤技术进行探究,以期为日后相关工作的顺利进行提供参考。
关键词: 综采;地质构造;分段回撤技术;安全性
中图分类号: TD823     文献标识码: A     文章编号: 2095-0802-(2020)07-0152-02
Discussion on the Section Withdrawal Technology of Fully Mechanized Mining through
Geological Structure
XING Gang
(Weide Mufang Coal Mine Design Consulting Co., Ltd. of Shanxi, Taiyuan 030001, Shanxi, China)
Abstract: In the operation of fully mechanized mining face, it is often influenced by the exposed collapse column in the middle
part of the face, which leads to the failure of pushing mining. For this reason, it is necessary to introduce the section withdrawal
technology of mining through geological structure to improve the safety of fully mechanized mining face and reduce unnecessary
losses. Through the analysis of the actual cases and the comparison of the schemes, this paper explored the section withdrawal
technology of fully mechanized mining through geological structure, in order to provide a reference for the future work.

Key words: fully mechanized mining; geological structure; section withdrawal technology; safety