摘要: 煤矿开采过程中,由于工作面的位置变化,需对机电设备进行安装和拆除。安装拆除工艺不仅关系到施工效
率,还关系到安全性,为此,需做好煤矿机电设备安装拆除工作。分析了煤矿机电设备安装拆除工艺存在的问题,探讨
了煤矿机电设备安装拆除工艺的优化措施,可为煤矿机电设备的安装拆除工作提供一定的指导。
关键词: 煤矿;机电设备;安装拆除;工艺优化
中图分类号: TD407      文献标志码: A      文章编号: 2095-0802-(2022)10-0168-03
Optimization Design of Installation and Removal Process of Electromechanical Equipment in
Coal Mines
QIAO Ruisheng
(Jiexiu Yitang Anyi Coal Industry Co., Ltd. of Shanxi, Jiexiu 032000, Shanxi, China)
Abstract: In the process of coal mining, due to the change of the position of the working face, it is necessary to install and
remove the electromechanical equipment. The installation and removal process is not only related to the construction efficiency,
but also related to the safety. Therefore, it is necessary to do a good job in the installation and removal of electromechanical
equipment in coal mines. This paper analyzed the problems existing in the installation and removal process of electromechanical
equipment in coal mines, and probed into the measures to optimize the installation and removal process of electromechanical
equipment in coal mines, which can provide some guidance for the installation and removal of electromechanical equipment in
coal mines.

Key words: coal mine; electromechanical equipment; installation and removal; process optimization