益门煤矿综合机械化改造采区机电运输设计
发布人:网站管理员 发布时间:2023/11/9 点击次数:28次
  

益门煤矿综合机械化改造采区机电运输设计
廖宇
(凉山州益门煤业有限责任公司,四川 凉山 615104)
摘要: 综合机械化采煤改造是中小煤矿企业发展的必由之路。根据益门煤矿生产实践,对21 采区机械化升级改造中
的机电运输、供电系统进行方案设计、设备选型和结果验算。验算结果表明,21 采区机械化升级改造后所选用设备均能
满足开采需求,供电线路温升(载流量)、电压损失以及采区运输系统的提升能力、钢丝绳安全系数、刮板输送机的运
力等参数均满足规范要求。
关键词: 机械化改造;设备选型;电压损失;电力负荷;温升
中图分类号: TD822      文献标志码: A      文章编号: 2095-0802-(2023)10-0170-03
Design of Electromechanical Transportation in Fully-mechanized Transformation
Mining Area of Yimen Coal Mine
LIAO Yu
(Liangshan Yimen Coal Industry Co., Ltd., Liangshan 615104, Sichuan, China)
Abstract: Fully-mechanized coal mining transformation is the only way for the development of small and medium-sized coal
mining enterprises. Based on the production practice of Yimen Coal Mine, the scheme design, equipment selection and result
verification of the electromechanical transportation and power supply system in the mechanized upgrading and transformation of
the 21 mining area were carried out. The calculation results show that the selected equipment after the mechanization upgrade and
transformation of the 21 mining area can meet the mining needs, and the parameters such as temperature rise (carrying capacity)
and voltage loss of the power supply line, as well as the lifting capacity of the mining area transportation system, safety factor of
the steel wire rope, and the transportation capacity of the scraper meet the specification requirements.

Key words: mechanized transformation; equipment selection; voltage loss; electrical load; temperature rise